5. REMARKS ABOUT PROJECT DEVELOPMENT
|
Engineering
|
Piping design has been finished 80%
|
Procurement
|
PR of control valve issued
|
control valve have delivery BYC
|
Construction
|
TP construction and piping installation have finished during TAR(2012-4-30)
|
Site Quality & HSE
|
|
Areas of Concern
|
|
a piece of pipeline(incloding 2pc valves, 4pc flgs and 1m pipe) was been removed
by plant, then operators are looking for it.
|